CJSC EnergoFront delivered ahead of schedule a boiler feed pump unit to the Zainskaya State District Power Plant site
17 March 2014
CJSC EnergoFront delivered ahead of schedule the APE-580-195-5 boiler feed pump unit with the 4AZM-5000/6000-UHL4 electric motor to the Zainskaya State District Power Plant site. The equipment was supplied fully complete, with all technical documentation in accordance with the terms of the contract. The design of the pump included technical solutions to modernize the first stage guide vane, aimed at increasing its resistance to vibrations when operating in transient conditions and increasing the efficiency of the installation.
This pumping unit is part of the equipment modernization program for side No. 12 of Zainskaya GRES. In May-June 2014 installation work of the specified equipment is planned. Specialists from the service department of JSC EnergoFront will provide services for supervision of installation and commissioning of a pumping unit with an electric motor. The launch of the power unit is scheduled for July 2014.