At the Kovdorsky GOK, the implementation of an investment project to modernize electrical equipment continues
8 November 2012
At the Kovdorsky GOK, the implementation of an investment project to modernize electrical equipment continues, the purpose of which is to increase the productivity of the equipment operating at the plant.
As part of this project, the drives of the main conveyor LTMP-160-5000-2 of the DKK crushing plant section were replaced.
CJSC TorMashEnergo supplied new modern electric motors with a wound rotor 3АНС500Н8 produced by EVIG Elektromotor Energy Kft, Hungary. Acceptance of electric motors was carried out in several stages, including with the participation of customer representatives during acceptance tests of the manufacturer.