EnergoFront is expanding the geography of projects – it will supply feed and network pumping units produced by CNP for OK RUSAL Anode Factory LLC

8 July 2024

EnergoFront was recognized as the winner in the competition for the supply of boiler feed pumping units CMBG155-67×9 (for parameters: Q=150m3/h, H=580m) with electric motors – in the amount of 3 pieces and district heating water pumping units NSC200-150-460-160/4 (for parameters: Q=500m3/h, Н=70м) – 4 pieces for the needs of LLC OK RUSAL Anode Factory.

The proposed pumping units will be modified at the factory to be able to work together with frequency converters.

In this delivery we represent the interests of our manufacturing partner – CNP (CNP Rus). As part of the project for the construction of a thermal power plant for the Taishet Anode Factory, our specialists, having carefully studied the technical side of the issue, taking into account the peculiarities of pump operation, proposed the specified pumping units with increased reliability and efficiency, taking into account the necessary equipment in accordance with the technical requirements for delivery.

After delivery, our service specialists plan to carry out supervision of installation and supervision of commissioning of electric pump units.

With wishes of a reliable partnership,

EnergoFront team #FrontProject

Long production hall with yellow overhead crane and rows of equipment