13.05.2025
Overhaul of fluid coupling at Kharanorskaya GRES
As part of the planned shutdown of power unit No. 3 of the Kharanorskaya GRES, specialists from the EnergoFront company carried out a major overhaul of the VOITH 682 SVNL 33G fluid couplings, which ensure the operation of the PEN-3A and PEN-3B boiler feed pumps. All work was carried out in strict accordance with the requirements
Learn more
-
07.05.2025
CONGRATULATIONS ON VICTORY DAY!
Congratulations to everyone on the majestic date - the 80th anniversary of Victory in the Great Patriotic War!
Learn more
-
22.04.2025
Tests confirm: the innovative fluid coupling is ready for use
At the production site of the Chinese manufacturer, critical testing of a new fluid coupling, developed as a replacement for VOITH equipment, has been completed.
Learn more
-
14.04.2025
“EnergoFront” at the VODEXPO-2025 exhibition
From April 8 to April 10, 2025, the IX All-Russian Water Congress and Exhibition “VODEXPO” was held in the Forum pavilion of the Expocentre Fairgrounds.
Learn more
-
10.03.2025
Supply of circulation pump 96DV-4.5/23 for the needs of the joint venture Khabarovsk CHPP-3
In order to avoid the risks of emergency situations at Khabarovsk CHPP-3, due to equipment failure, in conditions of urgent production need for the Customer, our company, together with the manufacturer JSC Uralgidromash, found the possibility of concluding a contract for the supply of a circulation pump 96DV-4.5/23 produced by JSC Uralgidromash with the shortest possible delivery time - September 2025 year.
Learn more
-
15.02.2025
EnergoFront will supply VAN-173/39-12KU3 electric motors for Iriklinskaya State District Power Plant
EnergoFront LLC was selected as a supplier for the supply of electric motors VAN-173/39-12KU3 (1000 kW, 500 rpm, 6 kW) in the amount of 2 pcs. for the needs of the Branch of Iriklinskaya State District Power Plant - JSC Inter RAO - Electric Power Plants. In this delivery we represent the interests of our long-time trusted partner
Learn more