An important milestone at Novolenskaya TPP: the first high-pressure boiler feed pump was tested and accepted
1 June 2026
The EnergoFront company reports an important stage in the implementation of the strategic project to equip the Novolenskaya Thermal Power Plant under construction (Republic of Sakha-Yakutia). In the presence of representatives of the Customer – JSC Inter RAO – Electric Power Plants – the factory tests and acceptance of the first high-pressure boiler feed pump of the TDG670-215×10 series produced by Shanghai Kaiquan Pump were successfully completed.
This event confirms EnergoFront’s readiness to carry out the most complex engineering tasks under the conditions of sanctions restrictions and ensure the energy security of state-scale facilities.
Confirmation of the declared characteristics at the factory stand
The tests took place at the manufacturer’s factory bench. As part of the program, EnergoFront specialists together with the customer’s engineers confirmed:
-
Mode parameters: The pump has achieved the required flow (680 m³/h) and head (2145 m), which corresponds to the specifications of the turnkey project;
-
Efficiency: The efficiency of the unit is fixed at 81%;
-
Reliability: vibration diagnostics and control of cavitation reserve (10.5 m) were carried out when working with a high-temperature environment up to 160°C.
Particular attention was paid to checking the operation of the fluid coupling (smooth control system) and mechanical seals – critical components for trouble-free operation in the extreme climate of Yakutia.
Currently, the equipment (boiler feed pumps) is in mass production. Delivery of the entire line of PEN to the Novolenskaya TPP site is planned for 2026 in accordance with the facility commissioning schedule.
Let us recall that network pumping equipment for the same station has already been successfully shipped and delivered to the Republic of Sakha along a proven logistics route.
The Novolenskaya TPP project with a capacity of 550 MW is one of the key ones for the region’s energy system. The EnergoFront company acts here not just as a supplier, but as a strategic partner responsible for the full engineering cycle: from design and selection of manufacturers to testing and service support.
With wishes for stable development,
EnergoFront team #FrontProject