     LLC «EnergoFront» continues to inform you about the project of technical re-equipment of the heating plant SU «CHP-4» (the city of Omsk).

In May 2019, three Delium D350-530A-530 pumps have been tested with the participation of the Project Manager of LLC «EnergoFront» Evgeniy Lee and representatives of SU «CHP-4» JSC «TGC-11». Pumping units were tested at three design points, in each of which vibration and noise characteristics were measured.

ТЭЦ-4

In addition, hydraulic overpressure tests were carried out on the pumping units.

The audit showed full compliance with the stated requirements.

Delivery of pumping units will be performed in May 2019 for installation as network pumps of the second lifting on SU «CHP-4».